10:55
sept 13 - laid the vapour barrier - starting the infloor heating piping and rebar
HotNoob
Shared 27/09/2022
06:52
sept 12 - finishing the north footer forms - back filled - tractor needs repairs again
HotNoob
Shared 26/09/2022
09:15
sept 08 - dug out the north footer - finished bathroom plumbing - starting north footer forms
HotNoob
Shared 22/09/2022
06:30
sept 03 - update - more underslab plumbing - island drain - toilets bathroom
HotNoob
Shared 20/09/2022
14:21
aug 31 - nearly finished the radon system, weather is getting too hot, quick overview of plumbing an
HotNoob
Shared 05/09/2022
04:04
aug 29 - main plumbing assembly done - digging out the plumbing and radon system
HotNoob
Shared 02/09/2022
22:57
aug 24 - starting on the plumbing - a supplier screwed up the order big time - noob mistakes
HotNoob
Shared 01/09/2022
16:56
aug 06 - repairing rear blade on tractor - cleaning some metal for 3pt hitch mod
HotNoob
Shared 23/08/2022
20:44
july 30 - homestead update - got an sketchy rv, buying garbage, fixing generator
HotNoob
Shared 19/08/2022
03:47
june 23 - fixed tractor, backfilling old waterline - too wet to backfill
HotNoob
Shared 16/08/2022
03:48
june 15 - more rain - rain destroyed footer trenches - too much water to continue
HotNoob
Shared 15/08/2022
18:01
june 09 - starting to dig footers at new building site; foundation materials arrived
HotNoob
Shared 09/08/2022
13:42
June 07/22 - Digging for More Sandy Gravel - More Back Filling And Leveling
HotNoob
Shared 18/06/2022
25:19
June 06/22 - Prepping Foundation Ground - Back-Filling With New Soil - Hunting For Gravel
HotNoob
Shared 17/06/2022
15:35
June 04/22 - Restarting at The New Building Location-Prepping Ground -Removing Top Soil - TimeLapse
HotNoob
Shared 16/06/2022
12:41
May 31/22 - Overland Flood Approaching and Filling Buildsite - Homested
HotNoob
Shared 14/06/2022